We give your business the advantage it requires. From reducing the input costs of an existing business, to providing the required energy infrastructure to your newest venture, GRØNN can help you realise your business goals.

Commercial Systems: Our Products

OUR PROJECT EXPERIENCE

Motla%20-%20Cubby%20Solar%20-%20Photo%20

CHUBBY CHICK MAIN FACTORY

1454,5kWp - 2 025 979kWh

Chubby Chick decided to install a solar PV system in order to reduce their almost 2,5MVA of demand and associated energy bill. One of the many challenges in this installation is the various injection points and thus distributed nature of the PV system. This was addressed by installing a wireless mesh network across the site, collecting all the data to one central point, before uploading to Sunny Portal. This communications network also allows for feed-in control and integration with their diesel generator system. In total 26 x SMA CORE-1 and 4 x SMA STP25 inverters are installed across the site and connected to 4 480 Jinko modules. This installation includes a full lightning protection system and weather station. All working in perfect harmony to provide clean power to the facility.

DJI_0336_edited.png

CHUBBY CHICK PLANT 2

627kWp - 986,2MWh

Grid-tied roof mounted PV system with diesel integration and performance ratio monitoring. This system uses 11 x SMA CORE-1 50kW inverters and 1 697 x 370W monocrystaline modules.

DJI_0092_edited.jpg

CHUBBY CHICK HATCHERY A & B

474,7kWp - 759,8MWh & 199,8kWp - 320,4MWh

Grid-tied roof mounted PV system with diesel integration and performance ratio monitoring. Hatchery A uses 8 x SMA CORE-1 50kW inverters and 1283 x 370W monocrystaline modules. hatchery B uses 3 x SMA CORE-1 50kW inverters and 540 x 370W monocrystaline modules.

DJI_0632.JPG

MOOIRIVIER JUNCTION

616kWp - 982 200kWh

Sustainability was a key requiremenet when construction began on this new shopping centre in Potchefstroom. The development group decided to install a solar PV system to reduce their carbon footprint. The system consists of the first 5 x SMA STP110 CORE-2 inverters installed in South Africa and 616 x 440W modules. This accounts for 48% of the total energy requirements.

IMG_20160509_114105_edited.jpg

SENWES HEAD OFFICE

753,5kWp - 828 828kWh

After significantly reducing their load through various energy efficiency initiatives, Senwes decided to install a solar PV system to further reduce their energy cost and carbon footprint. This system uses 2 392 Trina modules connected to 30 x SMA STP25 inverters to provide 100% of their power during the peak sun hours. In addition the weather station and Sunny Portal provide online monitoring capabilities. Using an advanced control system the PV has also been integrated with the standby generator system. Making this office facility green, smart and ready for the future.

DJI_0113_edited.jpg

SENWES HENNENMAN SILO

358,4kWp - 472 371kWh

As part of their long term strategy to manage energy cost and reduce their carbon footprint, Senwes Grainlink has decided to pioneer the installation of a solar PV system at their Hennenman grain silo. This installation is the first solar PV installation in the Southern Hemisphere. Due to the expanded nature of the site a wireless communication network is installed to allow for feed-in control and integration with the diesel generator. Using 1 120 Jinko modules connected to  14 x SMA STP25 inverters, this PV system provides up to 100% of the power to the facility during peak sun hours.

DJI_0534.jpg

CORPUS NOVEM OFFICE PARK

263,6kWp - 402 700kWh

As part of their cost management program Corpus Novem has installed a 263kWp grid-tied solar PV system. This was done using 3 x SMA CORE-1 50kW inverter and 2 x SMA STP25 inverters. The inverters are powered by 753 x 350W modules. The system also features 0 export to council and provides 59% of their energy requirements.

DJI_0702_edited.jpg

CHUBBY CHICK HILLSIDE

126,72kWp - 209,3MWh

Grid-tied roof mounted PV system with performance ratio monitoring. The system consists of 2 x SMA CORE-1 50kW inverters and 384 x 330W modules. This accounts for 48% of the total energy requirements.

DJI_0593.JPG

4 WAYS MART

94,4kWp - 152 700kWh

Through the installation of a 94kWp grid-tied solar PV system the owners have reduced their grid consumption by 66%. This was achieved with 233 monocrystaline 405W modules. It also features 0 export to council.

DJI_0294_edited.png

ENGEN ALBERT LUTHULI

25,75kWp - 42 822kWh

The owners commissioned the installation of a 25,8kWp grid-tied solar PV system. Consisting of 80 x 330W panels and 1 x SMA STP25 inverter. Currently this system is operating with 0 export to council and is delivering 25% of the facility's energy requirements.

DJI_0264_edited.jpg

ENGEN MOOI RIVIER JUNCTION

31,6kWP - 51 002kWh

The owners commissioned the installation of a 31,6kWp grid-tied solar PV system. Using 80 of the latest 395W solar PV modules and 1 x SMA STP25 inverter. Currently this system is operating with 0 export to council and is delivering 27% of the facility's energy requirements.

DJI01046.JPG

SASOL GOUDKOP

25,8kWp - 39 526kWh

With the upgrading of the filling station the owners commissioned the installation of a solar PV system using 1 x SMA STP25 inverter and 100 Jinko modules. They are now saving up to 25% on their monthly energy bill.

DJI_0249_edited.jpg

EIKELAAN OLD AGE HOME

126kWp - 196 000kWh

As part of their cost management program Huis Eikelaan has installed a 126kWp grid-tied solar PV system. This was done using 1 x SMA CORE-1 50kW inverter and 2 x SMA STP25 inverters. The inverters are powered by 360 x 350W modules. The system also features 0 export and performance ratio monitoring. The PV system provides 49% of their energy requirements.

DJI_0162_edited.png

MAURY AVENUE

57kWp - 103 300kWh

Through the installation of a 57kWp grid-tied solar PV system the owners have reduced their grid consumption by 38%. This was achieved with 153 monocrystaline 370W modules. It also features 0 export and performance ratio monitoring.

DJI_0368_edited_edited.jpg

GOLDWING

52,8kWp - 84 750kWh

The company has installed a 52,8kWp grid-tied solar PV system which supplies 56% of their energy requirements. This is achieved with 1 x SMA CORE-1 50kW inverter paired with 160 x 330W modules. The system is setup with 0 export to council.

DJI_0741.JPG

MEYER & DWARS

29,7kWp - 48 290kWh

This is a grid-tied, roof mounted system with the goal of energy saving and future implementation of a storage component.

DJI_0438.JPG

WESTVAAL KLERKSDORP

51,5kWp - 83 688kWh

With the construction of their new showroom in Klerksdorp the Westvaal group decided to install a solar PV system to reduce their carbon footprint. Through the installation of 2 x SMA STP25 inverters and 160 Jinko modules they are operating 100% on solar power during peak sun hours.

DJI_0333_edited.jpg

KLERKSDORP RECORD

21kWp - 31 208kW

This is a grid-tied, roof mounted system with the goal of energy saving and future implementation of a storage component.

IMG_2958_edited.jpg

BDB AUDITORS

17,6kWp - 27 000kWh

The owner of BDB saw an investment opportunity in installing a solar PV system and renting out some of their office space. With the installation of a SMA STP17 inverter and 69 Jinko modules they have significantly reduced their monthly operating cost and increased the building profitability.

Picture 1.png

SAGGY STONE BREWERY

41,6kWp - 76 469kWh

Saggy Stone commissioned the installation of a solar PV system as part of their clean energy drive. With the installation of 2 x SMA STP20 inverters and 128 Jinko modules they are now saving up to 33% on their monthly energy bill.

DJI_0458_edited.jpg

JOHNSONS PLACE

17,16kWp - 28 700kWh

This is a grid-tied, roof mounted system with the goal of energy saving and future implementation of a storage component.

3.png

KANGO CLINIC

51kWp - 83 230kWh

The aim of the client was to reduce the monthly bill from the municipality and to feed as much energy into the grid as possible to sell to the municipality. The system consists of 173 x 330W Canadian Solar panels and 1 x SMA CORE-1 50kW inverter. The system is also monitored via Sunny Portal.

Screenshot 2020-05-27 at 12.38.21.png

HYSA - NWU

52kWp - 82 125kWp

Grid-tied, tilted roof mount system powering a Hydrogen test facility at the North West University Engineering Campus in Potchefstroom. Excess energy produced is fed into the local network and consumed by other facilities on site.